Public Works Department, Government of Karnataka
State Highway Development Project
Project Implementation Unit

 

Govt. Order No: PWD 45 EAP 2012 Dated:09-05-2012 and PWD 121 EAP 2012 Dated:19-11-2012

Road Length: In KMs                  Amount: In Crores

Administrative Approval

Technical Sanction

Actual Execution ( To the end of October 2025)

Improvement/

Renewal

Amount

Impro-

-vement

Renewal

Total

Amount

No. of Packages

Contract Amount

Impro-

-vement

Renewal

Amount

Revised Amount

3724.51

1439.24

2123

1447

3570

1439.24

66

1541.78

2270

1134

3404

1689

 

 

  • All the 66 Packages were completed
  • Rs1689.00 Crores have been spent so far
  • The remaining Rs 73.54 Crores have to be paid
  • The Revised Administrative Approval was given vide G.O No. PWD 156 EAP 2015 Bengaluru Dated: 23-06-2018  for Rs 1762.97  Crores

Click Here to Download the Progress Report under Phase I