Govt. Order No: PWD 45 EAP 2012 Dated:09-05-2012 and PWD 121 EAP 2012 Dated:19-11-2012
Road Length: In KMs Amount: In Crores
|
Administrative Approval
|
Technical Sanction
|
Actual Execution ( To the end of October 2025)
|
|
Improvement/
Renewal
|
Amount
|
Impro-
-vement
|
Renewal
|
Total
|
Amount
|
No. of Packages
|
Contract Amount
|
Impro-
-vement
|
Renewal
|
Amount
|
Revised Amount
|
|
3724.51
|
1439.24
|
2123
|
1447
|
3570
|
1439.24
|
66
|
1541.78
|
2270
|
1134
|
3404
|
1689
|
- All the 66 Packages were completed
- Rs1689.00 Crores have been spent so far
- The remaining Rs 73.54 Crores have to be paid
- The Revised Administrative Approval was given vide G.O No. PWD 156 EAP 2015 Bengaluru Dated: 23-06-2018 for Rs 1762.97 Crores
Click Here to Download the Progress Report under Phase I