The project is proposed to be taken up in two (2) phases.

Phase-1

  • Administrative Approval
    • State Government Order dated 09-May-2012 and 19-November-2012
    • Improvements of selected State Highways-3724 Kms
      • Improvements-2087.00 kms
      • Renewal -1637.00 kms
    • 66 Packages
    • Estimated cost Rs 1439.00 Crore.
  • Tenders
    • Technical and Financial Bid Evaluation for 63 packages is completed.
      • Retendered: 03 Packages
  • Budget Provision
    • Supplementary Budget Provision of Rs.200.00 crores was accorded under Plan 5054

Phase-2

  • Administrative Approval
    • State Government Order PWD 107 EAP 2012, Dated 19.03.2013
    • Improvements of selected State Highways-3745.00 Kms
    • 70 Packages
    • Estimated cost RS 1498.90 Crore.
  • Budget for 2012-2013
    • Administrative approval accorded for 66 packages costing Rs 1439 crore under Plan 5054
    • Budget provision of Rs.500.00 crores under Plan 5054-(P-69)& Rs73.05 lakhs under Non-Plan 3054(P-42)
  • Budget for 2013-2014
    • Budget provision of Rs.700.00 crores under Plan 5054 & Rs.3.44 crores under Non Plan 3054
    • Supplementary Budget Provision of Rs.400.00 crores under Plan 5054 & Rs.4.34 crores under Non Plan 3054
  • Budget for 2014-2015
    • Budget provision of Rs.477.40 crores under Plan 5054 & Rs.4.34 crores under Non Plan 3054
    • Supplementary Budget Provision of Rs.541.68 crores under Plan 5054
  • Budget for 2015-2016
    • Budget provision of Rs.900.00 crores under Plan 5054 & Rs.4.82 crores under Non Plan 3054
  • Expenditure Details:
    • 2011-12 Rs.17.75 Lakhs
    • 2012-13(Up to 31-March-2013) Rs.519.56 Crores under Plan 5054 & Rs.2.41 crores under Non Plan 3054
    • 2013-14(Up to 31-March-2014) Rs.1100.00 Crores under Plan 5054 & Rs.3.97 crores under Non Plan 3054
    • 2014-15 - Rs.1018.83 Crores under Plan 5054 & Rs.4.26 crores under Non Plan 3054
    • 2015-16 - Rs.850.00 Crores under Plan 5054 & Rs.4.08 crores under Non Plan 3054