Govt. Order No: PWD 183 EAP 2014 Dated: 30-12-2015
             Road Length: In KMs                   Amount: In Crores                   
	
		
			| 
			 Administrative Approval 
			 | 
			
			 Technical Sanction 
			 | 
			
			 Actual Execution 
			 | 
		
		
			| 
			 State Highway 
			 | 
			
			 MDR 
			 | 
			
			 Total 
			 | 
			
			 Amount 
			 | 
			
			 Length 
			 | 
			
			 Amount 
			 | 
			
			 No. of Packages 
			 | 
			
			 Contract Amount 
			 | 
			
			 Length 
			 | 
			
			 Revised Amount 
			 | 
		
		
			| 
			 2795 
			 | 
			
			 1520 
			 | 
			
			 4315 
			 | 
			
			 3500 
			 | 
			
			 4095.16 
			 | 
			
			 3500 
			 | 
			
			 127 
			 | 
			
			 3673.34 
			 | 
			
			 3800.74 
			 | 
			
			 3982.2 
			 | 
		
	
 
 
Yearwise Execution Details
	
		
			| 
			 Sl. No. 
			 | 
			
			 Year 
			 | 
			
			 Execution 
			 | 
		
		
			| 
			 Length 
			 | 
			
			 Expenditure 
			 | 
		
		
			| 
			 1 
			 | 
			
			 2016-17 
			 | 
			
			 1975 
			 | 
			
			 1193.78 
			 | 
		
		
			| 
			 2 
			 | 
			
			 2017-18 
			 | 
			
			 1394 
			 | 
			
			 1726.41 
			 | 
		
		
			| 
			 3 
			 | 
			
			 2018-19 
			 | 
			
			 297 
			 | 
			
			 686.76 
			 | 
		
		
			| 
			 4 
			 | 
			
			 2019-20 
			 | 
			
			 116.41 
			 | 
			
			 213.32 
			 | 
		
		
			| 
			 5 
			 | 
			
			 2020-21 
			 | 
			
			 17.92 
			 | 
			
			 10.27 
			 | 
		
		
			| 
			 Total 
			 | 
			
			 3800.7 
			 | 
			
			 3830.54 
			 | 
		
	
 
	- 123  Packages were completed and balance 4 Packages are under progress
 
	- Rs. 3830.54 Crores have been spent so far
 
	- The remaining 44 KMs of length of Road is to be completed for which Rs 33.27 Crores are required
 
	- The Revised Administrative Approval proposal was submitted to government.