Govt. Order No: PWD 304 EAP 2023 Bangalore Dated: 29.02.2024
Road Length: In KMs Amount: In Crores
|
Administrative Approval
|
Technical Sanction
|
Actual Execution( To the end of October 2025)
|
|
State Highway
|
MDR
|
Total
|
Amount
|
Length
|
Amount
|
No. of Packages
|
Contract Amount
|
Length
|
Revised Amount
|
|
1045.69
|
458.68
|
1503.38
|
4000
|
1511.71
|
3786.73
|
218
|
3885.49
|
646.04
|
429.83
|
- 28 Packages were completed and balance 190 Packages are under progress
- Rs. 527.11 Crores have been spent so far
Click Here to Download the Progress Report under Phase V Stage 1