Govt. Order No: PWD 107 EAP 2012 Dated: 19-03-2013
Road Length: In KMs &, Amount: In Crores
Road Length: In KMs Amount: In Crores
|
Administrative Approval
|
Technical Sanction
|
Actual Execution (To the end of October 2025)
|
|
Improv-
-ement
Renewal
|
Amount
|
Impro-
-vement
|
Renewal
|
Total
|
Amount
|
No. of Packages
|
Contract Amount
|
Impro-
-vement
|
Renewal
|
Amount
|
Revised Amount
|
|
3745
|
1498.90
|
2258
|
1247
|
3505
|
1431.61
|
70
|
1695.47
|
2425.63
|
710.43
|
3136.06
|
1869.00
|
- All the 70 Packages were completed
- Rs. 1869 Crores have been spent so far
- The remaining Rs 23.87 Crores have to be paid
- The Revised Administrative Approval proposal was submitted to government on 22-01-2021
Click Here to Download the Progress Report under Phase I