Govt. Order No: PWD 188 EAP 2020 Bangalore Dated: 03.1.2022
Road Length: In KMs Amount: In Crores
|
Administrative Approval
|
Technical Sanction
|
Actual Execution ( To the end of October 2025)
|
|
State Highway
|
MDR
|
Total
|
Amount
|
Length
|
Amount
|
No. of Packages
|
Contract Amount
|
Length
|
Revised Amount
|
|
1148.26
|
1127
|
2275.26
|
3500
|
2245.80
|
3001.60
|
178
|
3518.69
|
2203.41
|
4000.58
|
- 154 Packages were completed and balance 24 Packages are under progress
- Rs. 3892Crores have been spent so far
Click Here to Download the Progress Report under Phase IV Stage 2