Govt. Order No: PWD 183 EAP 2014 Dated: 30-12-2015
Road Length: In KMs Amount: In Crores
Administrative Approval
|
Technical Sanction
|
Actual Execution
|
State Highway
|
MDR
|
Total
|
Amount
|
Length
|
Amount
|
No. of Packages
|
Contract Amount
|
Length
|
Revised Amount
|
2795
|
1520
|
4315
|
3500
|
4095.16
|
3500
|
127
|
3673.34
|
3800.74
|
3982.2
|
Yearwise Execution Details
Sl. No.
|
Year
|
Execution
|
Length
|
Expenditure
|
1
|
2016-17
|
1975
|
1193.78
|
2
|
2017-18
|
1394
|
1726.41
|
3
|
2018-19
|
297
|
686.76
|
4
|
2019-20
|
116.41
|
213.32
|
5
|
2020-21
|
17.92
|
10.27
|
Total
|
3800.7
|
3830.54
|
- 123 Packages were completed and balance 4 Packages are under progress
- Rs. 3830.54 Crores have been spent so far
- The remaining 44 KMs of length of Road is to be completed for which Rs 33.27 Crores are required
- The Revised Administrative Approval proposal was submitted to government.