Govt. Order No: PWD 107 EAP 2012 Dated: 19-03-2013
Road Length: In KMs &, Amount: In Crores
Administrative Approval
|
Technical Sanction
|
Actual Execution
|
Improvement/
Renewal
|
Amount
|
Improvement
|
Renewal
|
Total
|
Amount
|
No. of Packages
|
Contract Amount
|
Improvement
|
Renewal
|
Amount
|
Revised Amount
|
3745
|
1498.90
|
2258
|
1247
|
3505 |
1431.61
|
70
|
1695.47
|
2425.63
|
710.43
|
3136.06
|
1859.92
|
Yearwise Execution Details
Sl. No.
|
Year
|
Execution
|
Improvement
|
Renewal
|
Total
|
Expenditure
|
1
|
2013-14
|
500
|
305
|
805
|
329.42
|
2
|
2014-15
|
1197
|
329
|
1526
|
799.23
|
3
|
2015-16
|
712
|
76
|
788
|
693.15
|
4
|
2016-17
|
17
|
-
|
17
|
26.91
|
5
|
2017-18
|
-
|
-
|
-
|
1.66
|
6
|
2018-19
|
-
|
-
|
-
|
9.55
|
Total
|
2426
|
710
|
3136
|
1859.92
|
- All the 70 Packages were completed
- Rs. 1853.99 Crores have been spent so far
- The remaining Rs 37.78 Crores have to be paid
- The Revised Administrative Approval proposal was submitted to government on 22-01-2021